JOINT BASE ANDREWS FUEL PIER LOADING PLATFORM RELOCATION

JOINT BASE ANDREWS FUEL PIER LOADING PLATFORM RELOCATION
ANACOSTIA RIVER, WASHINGTON DC

Client: NuStar Energy, L.P.

Project Start:                November 30, 2017
Project Completion:   July 31, 2018

Marine Technologies, Inc. Key Personnel:
Project Manager:                Howard Sprinkle
Project Superintendent:    Mike Williams

Owner's Representative:  Vince Donahue
Phone:   7267-304-5847

This project consisted of relocating the dock manifold downstream a distance that is equal to the distance that the downstream edge of the bridge is shifted.   The scope of relocation work included, but was not limited to: the supply and installation of thirteen 12" diameter steel pipe poles plumb; eight 14" diameter steel pipe piles battered; dynamic pile testing and re-strike; construction of two each upstream and downstream mooring dolphins; supply and installation of two each steel framing and installation of owner-supplied mooring bollard; installation of two each owner-supplied fender systems; installation of piping from the manifold location to shore; and installation of lights on the walkway.

An MTI marine survey crew performed the pre-construction side scan sonar. When
construction was completed but prior to demobilization a post-construction scan was performed to document any changes or debris.  MTI removed all underwater debris deemed by the owner to pose a threat to navigation.

 

JBA Fuel Pier (2)

 